Advanced Manufacturing Center
Advanced Manufacturing Center
At the Advanced Manufacturing Center, students will receive hands-on training in state-of-the-art labs, preparing them for careers in manufacturing, engineering, technology and technical trades. Other features include:
- An expanded Boeing pre-employment training program with dedicated sheet metal and fabrication classrooms
- A collaborative maker space for students, entrepreneurs and small businesses to learn and develop their trades
- Program visibility through large picture windows and glass walls to encourage safe and engaging tours for prospective students and the community
Project Updates
Stay in the know with the Advanced Manufacturing Center's latest milestones as the construction phase progresses.
Main Lobby Stairs and Windows
Oct. 2024—Contractors started installing curbs and sidewalks around the building. They completed window installation for the main lobby and the stairs leading from the lobby to the upper level. Other work included continued painting on the main level, drywall on the lower level, and bathroom flooring and tilework throughout.
Drywall and Painting
Sept. 2024—Painting and ceiling installation kicked off on the main level, while drywall started on the lower level. Throughout the entire building, contractors installed interior garage doors and mechanical pipes. Plumbing subcontractors installed lines on the lower level and worked on insulating pipes on all levels. Roofers continued installing the smaller green roof.
Progress and Another Milestone
Aug. 2024—Contractors worked on drywall and ductwork installation, completing the large duct and insulation on the main level in late August. They also completed framing for the canopy over the northeast entrance as well as the exterior brickwork. Detailing on the skylight started in mid-August. With skylights and flashing installed, the building is officially dried in.
Skylight Installed
July 2024—The feature skylight was blocked, framed and installed in July. Contractors completed most of the building's interior framing, installed windows on the western side, and set steel for the exterior stairs. They also installed drywall, water and sanitary lines, mechanical ductwork, and electrical piping.
Green Roof Prep and Windows
June 2024—Ironworkers installed curb posts on the green roof and completed their work on the main stairs. Window installation wrapped up on the south side and moved to the west side while contractors continued work on the roof installation, drywall, and exterior brick veneer.
Windows and Main Stairs
June 2024—In early June, contractors started installing windows on the south side of the building. They also installed the stairs that will serve as a place to hang out and host events and classes. Other progress included the roof, exterior veneer, air barrier, interior wall framing, and prep for permanent power.
Skylight Steel and Overhead Progress
May 2024—In late May, contractors worked on completing the steel for the building's feature skylight. They also installed sprinklers, roofing, and rough-ins for overhead plumbing. Other overhead work included mechanical rough-ins and electrical piping. Interior wall framing continued and is nearly complete on the main level.
Interior Framing Progress
May 2024—In early May, contractors completed most of the main level's interior wall and door frame installation, with the framing layout started for the upper level. Exterior masonry veneer work continued following behind the installation of the air vapor barrier. Mechanical, electrical and plumbing work continues throughout the building.
Iron Work Moving Along
April 2024—Ironworkers finished installing the western staircase and roof decking. Next up for them will be the skylight steel installation and minor detailing. Contractors continued interior framing, air vapor barrier installation, and mechanical, electrical, and plumbing rough-ins. Masons worked on installing interior walls on the lowest level and masonry veneer on the exterior western and southern walls.
Slab Pours and Masonry
March 2024—Decking installation and exterior framing continued. Concrete pouring also continued and slab-on-deck prep was started for the upper level. Interior lower-level masonry walls were completed on the east end of the building, and work began on the exterior walls on the west end.
Last of Steel Arrives
Feb. 2024—Contractors worked on steel installation with the last load of steel arriving at the end of the month. They also started pouring deck slabs and made significant progress on footings and interior CMU walls.
Beam Signing and Placement
Feb. 2024—The steel superstructure is nearly complete. To celebrate this milestone, the campus community was invited to add their signatures to a significant support beam and then watch as it was placed in its forever home.
Steel Erection Work
Jan. 2024—Contractors worked on steel erection for the new building and continued masonry on structural walls. They are also now preparing to start pouring slabs on deck in early February.
Slab Pour Milestone
Dec. 2023—A milestone was hit in mid-December with the pouring of the foundational slab. Structural concrete is approximately 85% complete, with both stair and elevator cores finished. Underground mechanical, electrical and plumbing installation was also completed.
Concrete Walls and Utility Tie Ins
Nov. 2023—Concrete wall installation continued on the south side of the building. 80% of foundations are now complete. High pressure piping was also completed at the tunnel tie in between the Administration and PE buildings. Backfilling this area is now underway and ahead of schedule.
Foundation Work Continues
Oct. 2023—Contractors continue to work on the foundation and started utility tie-in work. Utility tie-ins will take about eight weeks. Contractors also began elevator and stairwell tower installation.
Aggregate Pier Installation
Sept. 2023—Excavation continues as preparations begin for aggregate piers, which will
support the new building, and utility work.
Groundbreaking
Aug. 2023—The College broke ground on the center on Aug. 18. More than 100 guests
attended, including two robots courtesy of Rolla High School Robotics teams and a
drone, highlighting some of the future building's programs.
Excavation Begins
Aug. 2023—Contractors start the excavation process on the old parking lot to make
way for the future Advanced Manufacturing Center.
Building Renderings
Get an inside look at the anticipated features of the new facility.
Grand Stand Main Level View
Aerial of Building and Plaza
3D Print Lab
Explore the Advanced Manufacturing Center with this flythrough tour.
Key Facts
Anticipated Completion: Winter 2024
Size: 96,000 square feet
Estimated Cost: $61.1 million
Architect: JEMA
Construction Manager: Navigate Building Solutions
Contractor: Kadean Construction Company
Program offerings include:
- Boeing Pre-Employment Training
- Industrial Maintenance Technician
- Certified Welding Technician
- Computer Integrated Manufacturing
- Precision Machining Technology
- Skilled Trades Industrial Occupations Technology
- HVAC Operator I Technical Training
- Biomedical Electronics Technology
- Electrical/Electronic Engineering Technology
- Geospatial Technology
- Engineering Technology
- General Maintenance Mechanic
Contact Us
Have a question about STLCC Transformed? Please use this contact form to submit any questions or concerns.
For more information on the College's latest projects and proposals, please contact STLCC's engineering and design team.