Nursing and Health Sciences Center
Nursing and Health Sciences Center
The Nursing and Health Sciences Center will expand capacity for programs like nursing, dental hygiene and radiology technology. Other features include:
- The College's first ever bachelor's degree in respiratory care
- State-of-the-art equipment and simulator labs to prepare students for careers as EMTs and paramedics
- Dedicated areas for students to study, eat and hang out, including an outdoor plaza
Project Updates
Stay in the know with the latest milestones at the Nursing and Health Sciences Center as the construction phase progresses.
Structural Concrete Complete
March 2024—Pouring concrete continued in March, with the last structural pour completed at the end of the month. Interior wall framing continued and is now close to 85% complete. Drywall installation is ongoing.
Concrete Floor Install Wraps Up
Feb. 2024—Contractors worked on pouring the remaining deck slabs in February with a goal to complete concrete floors by mid-March. Contractors also continued mechanical, electrical and plumbing work, as well as the installation of the exterior vapor barrier.
Building Gets a Roof
Jan. 2024—The month wrapped up with pouring the roof slab and the drywall starting to go in priority areas. More than half of the building also has completed concrete slabs, and progress was made on exterior framing and sheeting installation.
Beam Signing and Placement
Jan. 2024—The steel superstructure is nearly complete. To celebrate this milestone, the campus community was invited to add signatures to a significant support beam and then watch as it was placed in its forever home.
Slab Pour Milestone
Dec. 2023—A significant milestone was reached in mid-December, pouring nearly 500 yards of concrete slabs on deck and grade. Steel erection is ongoing, while mechanical, electrical and plumbing trades work on rough-ins.
Steel and Piping Progress
Nov. 2023—Contractors reached the building’s fourth floor with steel installation. High pressure piping was completed and insulated with backfill underway in the parking lot west of Communications.
Framework Going Up
Oct. 2023—Construction continued to move along on the Nursing and Health Sciences
Center. Foundation and utility work was ongoing, while the building's frame started
going up in late October.
Aggregate Piers and Site Demo
Sept. 2023—Aggregate pier installation continued and was completed mid-month. The
billboard was also removed, which was the last item needed to complete site demo for
the building pad.
Construction Begins with Excavation
Aug. 2023—The construction phase kicked off with excavation the first week of August.
On Aug. 23, contractors began drilling and installing aggregate piers to reinforce
the ground.
Groundbreaking
July 2023—STLCC broke ground on the Nursing and Health Sciences Center on Wednesday,
July 19. College officials were joined by STLCC employees, building partners, community
leaders and public members.
Building Renderings
Get an inside look at the anticipated features of the new facility.
Entrance Vestibule
View from Pershall Road and 270
Student Lounge
Key Facts
Anticipated Completion: Winter 2024
Size: 100,000 square feet
Estimated Cost: $62.4 million
Architect: KAI Enterprises
Construction Manager: Navigate Building Solutions
Contractor: PARIC Corporation
Program offerings include:
- Respiratory Care
- Nursing
- Dental Hygiene
- Radiologic Technology
- Deaf Communication Studies
- Behavioral Health Support
- Emergency Medical Technology
- Paramedic Technology
- Licensed Practical Nursing
- Medical Assistant
- Patient Care Technician
Contact Us
Have a question about STLCC Transformed? Please use this contact form to submit any questions or concerns.
For more information on the College's latest projects and proposals, please contact STLCC's engineering and design team.